Condition 32: surface-water drainage

Church Street, Cliffe. Condition discharged.

The register entry

Condition 32: surface-water drainage, Church Street, Cliffe

Condition discharged
Homes gateway decisionDeveloper Esquire Developments

Details submitted to discharge condition 32. As amended, condition 32 bars development in any phase or sub-phase, highway works excepted, until a surface-water drainage scheme is approved. Medway approved it on 15 September 2026 under delegated powers, thirteen days before its own target date. It discharged the condition “for ALL PHASES”. The decision notice gives one reason: “the submitted information has been reviewed, and it is considered that the details are acceptable”. It refers to none of the twelve objections made on the application. No officer report, consultee response or habitats screening has been published with it. The Phase 2 investigation filed by the applicant had said shallow soakaways into the Seaford Chalk would not be a viable option for disposing of surface water. On 16 September 2026 the group’s committee wrote to the case officer asking Medway to publish its record of the decision, to answer twelve questions in writing and to say by 30 September 2026 whether it will look at the decision again.

  • Where the surface water from the site actually goes
  • A possible pathway to the Thames Estuary and Marshes Ramsar site
  • Whether one approval can stand for every phase of the development

Consultation ended 4 September 2026 — still undecided

View MC/26/1459 on the portal (opens in a new tab)Read the group’s letter on MC/26/1459 (opens in a new tab)Checked 2026-10-09

Noticeboard

What the group has said about it

Newest first. The full noticeboard is on the main page.

Newsletter, 18 September: one approved, eleven still waiting

Six pages, in plain English. The drainage scheme under MC/26/1459 was approved on 15 September and the committee has asked Medway to look at it again. Eleven applications on the Church Street land are still undecided. The group’s objections of 9 September to MC/26/1720 to MC/26/1724 are not yet on Medway’s public file, though all five can be read here. The recreation ground closes on 24 September and six more close on 1 and 2 October.

Read the newsletter: Newsletter, 18 September: one approved, eleven still waiting (opens in a new tab)

Medway approves the drainage scheme, MC/26/1459

Medway discharged condition 32 on 15 September 2026, approving the surface-water drainage scheme for every phase of the Church Street development. The decision was taken by officers, thirteen days before Medway’s own target date. Its notice gives a single reason: that the details are acceptable. It mentions none of the twelve objections made on the application. No officer report, consultee response or habitats screening has been published with it. Condition 32 was one of the conditions stopping development from starting. It no longer is. Others still are, including the construction management plan under condition 9.

The decision notice on Medway’s file: Medway approves the drainage scheme, MC/26/1459 (opens in a new tab)

The group asks Medway to look at the drainage decision again

On 16 September 2026 the group’s committee wrote to the case officer for MC/26/1459, copied to Medway’s Chief Planning Officer and Head of Development Management, Natural England, the parish council and the three ward councillors. The letter says the group could find no timetable for the drainage, no maintenance plan and no named owner for the basins, all of which condition 32 asks for. It says nothing on the file shows that the effect on the Ramsar site was screened or that the Environment Agency was consulted, although the developer’s own ground engineers advised that it must be. It asks Medway to publish its record of the decision, to answer twelve questions in writing and to say by 30 September whether it will look at the decision again. Residents have no right of appeal against a planning decision, so the letter asks Medway itself to reconsider.

Read the group’s letter: The group asks Medway to look at the drainage decision again (opens in a new tab)

Formal representation filed on all five applications

The group has filed its formal representation with Medway’s Principal Planning Officer, copied to the case officer for MC/26/1459, to Natural England and to the parish council. It does not seek to reopen the principle of development. It asks Medway to decide expressly whether each of the five decisions authorises the project, or a phase of it, to proceed — and if so, to carry out and publish the habitats assessment before granting them.

Why the drainage application matters most

The ground investigation the applicant filed says shallow soakaways into the chalk are not a viable option for disposing of surface water. Medway’s Strategic Flood Risk Assessment records that ditches across Cliffe Marshes drain into the Thames. So the practical question on MC/26/1459 is simple: where does the surface water go and does that route reach the protected wetland?

How we got here

Where it sits in the story

  1. Five applications land together

    MC/26/1459, MC/26/1465, MC/26/1466, MC/26/1467 and MC/26/1542 — drainage, three sets of reserved matters and remediation.

  2. Medway approves the drainage scheme

    Officers discharge condition 32 on MC/26/1459 for every phase, thirteen days before Medway’s own target date. The notice gives one reason: that the details are acceptable. It refers to none of the twelve objections.

The same land

The other applications on this site

All made under MC/22/0254, the outline permission allowed on appeal in November 2023.